"The Plan Risk Management process should begin and should be completed ."

"The Plan Risk Management process should begin and should be completed ."



A. When a project is conceived, early during project planning
B. Early during project planning, When a project is conceived
C. When a project is closed, early during requirement phase
D. Early in the morning, at night


Answer: A