"The scope management plan can be __ ."

"The scope management plan can be __ ."



A. Formal only
B. Informal only
C. Formal or informal
D. Excel only


Answer: C

The ___ is sometimes viewed as including _____ .

The ___ is sometimes viewed as including _____ .



A. Product scope, project scope
B. Project scope, product scope
C. Project tools, project scope
D. Project techniques, product scope


Answer: B

What is product scope?

What is product scope?



A. The quality objectives that characterize a product, service, or result
B. The activities to implement project as a whole
C. The features & functions that characterize a product, service, or result
D. The work that must be performed to complete one function


Answer: C

You are collecting requirements for your project. What will you obtain from Project Charter?

You are collecting requirements for your project. What will you obtain from Project Charter?



A. The high-level description of the product, service, or result of the project so that detailed requirements can be developed.
B. The detailed description of the product, service, or result of the project
C. The impact of any change or deviation from the scope baseline on objectives.
D. The work that must be performed to complete one or two functions


Answer: A

"The requirement traceability matrix helps to detect _____ ."

"The requirement traceability matrix helps to detect _____ ."



A. The impact of any change or deviation from the scope baseline on the project objectives.
B. Which type of requirements need to be collected for the project.
C. The work that must be performed to complete one or two functions
D. A set of conditions that is required to be met before deliverables are accepted


Answer: A

Requirements can be grouped into some classifications, one of them is project requirements. What does project requirements describe?

Requirements can be grouped into some classifications, one of them is project requirements. What does project requirements describe?



A. The actions, processes, or other conditions the project needs to meet
B. The behaviors of product, data, interactions with product
C. The temporary capabilities, data conversion &
training requirements
D. The higher-level need of organization as a whole


Answer: A

"The key benefit of creating WBS is that ______ ."

"The key benefit of creating WBS is that ______ ."



A. It provides a structured vision of what has to be delivered.
B. It provides a set of conditions that is required to be met
C. It provides type of requirements need to be collected
D. It provides a change or deviation from the scope baseline


Answer: A

Requirement should be _________ .

Requirement should be _________ .



A. Short & easy to guess
B. Long & complex
C. Measurable & testable
D. Functional only


Answer: C

You are managing project in coding phase & customer ask to add some changes in GUI of website homepage. When implementing & managing the actual changes, you also manage their integration with the other control processes. What are you doing?

You are managing project in coding phase & customer ask to add some changes in GUI of website homepage. When implementing & managing the actual changes, you also manage their integration with the other control processes. What are you doing?



A. Validate scope
B. Control scope
C. Define scope
D. Check scope


Answer: B