The project manager leading a training project is trying to decide on an approach for determining an earned value for the project management activities on the project. Which of the following approaches would be the best option for her to choose for these activities?

The project manager leading a training project is trying to decide on an approach for determining an earned value for the project management activities on the project. Which of the following approaches would be the best option for her to choose for these activities? 




A. Level of effort
B. Weighted milestones
C. Fixed formula, 50/50 value
D. Apportioned value



Answer: A