What is an RACI used for?

What is an RACI used for?



A. Performance analysis
B. Recording configuration items
C. Monitoring services
D. Defining roles and responsibilities


Answer: D

Which of the following BEST describes an Incident?

Which of the following BEST describes an Incident?



A. An unplanned disruption of service unless there is a backup to that service
B. An unplanned interruption to service or reduction in the quality of service
C. Any disruption to service whether planned or unplanned
D. Any disruption to service that is reported to the service desk , regardless of whether the service is impacted or not


Answer: B

Which of the following BEST describes a Problem?

Which of the following BEST describes a Problem?



A. The incident impacts many users
B. The same incident occurs many times
C. Both A & B are correct
D. Both A & B are not correct


Answer: C

Which of the following is NOT a valid objective of problem management?

Which of the following is NOT a valid objective of problem management?



A. To prevent problems and resulting incidents from happening
B. To eliminate recurring incidents.
C. To restore service to a user
D. To minimize the impact of incidents that cannot be prevented


Answer: C

Which of the following BEST describes the purpose of access management?

Which of the following BEST describes the purpose of access management?



A. To provide a channel for users to request and receive standard services
B. To grant authorized users the right to use a service of the application under maintenance, while preventing non-authorized users from accessing
C. To prevent problems and resulting incidents from happening
D. To detect security events and make sense of them


Answer: B

Which process ensures that : - Standardized methods and procedures are used for efficient and prompt handling of all changes - All changes to service assets and configuration items are recorded in the Configuration Management System - Overall business risk is optimized?

Which process ensures that :
- Standardized methods and procedures are used for efficient and prompt handling of all changes
- All changes to service assets and configuration items are recorded in the Configuration Management System
- Overall business risk is optimized?




A. Change management
B. Configuration management
C. Service Level Management
D. Problem Management.


Answer: A

What is the responsibility of the Project QA in a Scrum project?

What is the responsibility of the Project QA in a Scrum project?



A. To define and recommend process improvement
B. To verify process compliance with the project's defined processes
C. To provide training about process if necessary
D. All of the answers"


Answer: D

What is a key feature of Self-organizing teams?

What is a key feature of Self-organizing teams?



A. They organize and manage their work by themselves
B. They are independent organizations
C. They decide definition of done by themselves
D. They possess all required skills to create the products"


Answer: A

Which statement is TRUE about Definition of Done (DoD)?

Which statement is TRUE about Definition of Done (DoD)?



A. DoD is defined by Product Owner only
B. DoD is defined by Development Team only
C. DoD is to assess the performance of team
D. DoD must be shared with the whole Scrum Team"


Answer: D

Which of the followings is the best sample of Definition of Done (DoD)?

Which of the followings is the best sample of Definition of Done (DoD)?



A. Code built, Unit tests written, Integration test run
B. All defined tasks are complete
C. Code complete, Test complete & passing, agreement from Product Owner
D. Functions work well as required"


Answer: C

What should be the reasons for Sprint cancellation?

What should be the reasons for Sprint cancellation?




A. The Sprint goal is outdated
B. The organization changes business direction
C. The technology changes
D. All of the answers"


Answer: D

What is the purpose of Product Backlog Refinement?

What is the purpose of Product Backlog Refinement?



A. To archive the Product Backlog
B. To revise the Product Backlog
C. To validate the Product Backlog
D. To make up the Product Backlog


Answer: B