What is Stakeholders engagement assessment matrix is used for?

What is Stakeholders engagement assessment matrix is used for?



A. To identify the gaps between Planned engagement level and Desired engagement level
B. To identify the gaps between Requested engagement level and Desired engagement level
C. To identify the gaps between Current engagement level and Desired engagement level
D. To identify the gaps between Current engagement level and Assured engagement level


Answer: C

How is Information Management System used to control stakeholder engagement?

How is Information Management System used to control stakeholder engagement?



A. It allows the project manager to store project information
B. It allows the project manager to consolidate reports
C. It allows the project manager to distribute reports to the stakeholders
D. All of the answers


Answer: D

What is an activity of the Control Stakeholder Engagement process?

What is an activity of the Control Stakeholder Engagement process?



A. Planning strategies for engaging stakeholders
B. Clarifying and resolving issues
C. Adjusting strategies for engaging stakeholders
D. Negotiating with the stakeholders"


Answer: C

Which process uses Work Performance Data as an input?

Which process uses Work Performance Data as an input?



A. Control Stakeholder Engagement
B. Plan Stakeholder Engagement
C. Manage Stakeholder Engagement
D. Identify Stakeholders"


Answer: A

Who should be closely managed in stakeholder management?

Who should be closely managed in stakeholder management?



A. The stakeholders have Low power and High interest
B. The stakeholders have High power and Low interest
C. The stakeholders have High power and High interest
D. The stakeholders have Low power and Low interest"


Answer: C

Which statement is CORRECT about the engagement level of stakeholders?

Which statement is CORRECT about the engagement level of stakeholders?



A. The engagement level of stakeholders doesn't change through the project duration
B. The engagement level of stakeholders should be changed at each stage of project
C. The engagement level is the same for all stakeholders and at every stage of project
D. None of the answer"


Answer: B