Which of the following is TRUE regarding services scheduling?

Which of the following is TRUE regarding services scheduling?



A) The critical ratio sequencing rule is widely used for fairness to customers.

B) The emphasis is on staffing levels, not materials.

C) Reservations and appointments are often used to manipulate the supply of services.

D) Labor use can be intensive, and labor demand is usually stable.

E) All of the above are true.



Answer: B) The emphasis is on staffing levels, not materials.

Which of the following is a limitation of rules-based dispatching systems?

Which of the following is a limitation of rules-based dispatching systems?



A) Rules need to be revised to adjust to changes in orders, product mix, and so forth.

B) Rules may not recognize idle resources.

C) Rules may not recognize bottleneck resources

D) Rules may not be able to prioritize two jobs with identical due dates.

E) All of the above are limitations.



Answer: E) All of the above are limitations.

Which of the following is an advantage of the FCFS dispatching rule when used in services?

Which of the following is an advantage of the FCFS dispatching rule when used in services?



A) FCFS maximizes utilization.

B) FCFS minimizes the average number of jobs in the system.

C) FCFS minimizes the average lateness of all jobs.

D) FCFS maximizes the number of jobs completed on time.

E) FCFS seems fair to customers.



Answer: E) FCFS seems fair to customers.

Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours, and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and the average number of jobs in the system is ________.

Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours, and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and the average number of jobs in the system is ________.



A) 100 percent; 10.625

B) low; .0941

C) 0.400 or 40 percent; 2.5

D) 0.235 or 23.5 percent; 4.25

E) maximized; minimized



Answer: C) 0.400 or 40 percent; 2.5

Average completion time for a schedule sequence at a work center is the ratio of:

Average completion time for a schedule sequence at a work center is the ratio of:



A) total processing time to the number of jobs.

B) total flow time to total processing time.

C) total flow time to the number of jobs.

D) total processing time plus total late time to the number of jobs.

E) total flow time plus total late time to the number of jobs.



Answer: C) total flow time to the number of jobs.

Which of the following dispatching rules tends to minimize job flow time?

Which of the following dispatching rules tends to minimize job flow time?



A) FCFS: first come, first served

B) SPT: shortest processing time

C) EDD: earliest due date

D) LPT: longest processing time

E) FCLS: first come, last served



Answer: B) SPT: shortest processing time

Flow time represents the time:

Flow time represents the time:


A) an order spends waiting for processing at a work center.

B) an order spends being processed at a work center.

C) an order spends moving from one work center to another.

D) to complete an order, including time spent in processing and in waiting.

E) none of the above



Answer: D) to complete an order, including time spent in processing and in waiting.

Sequencing (or dispatching):

Sequencing (or dispatching):



A) assigns dates to specific jobs or operations steps.

B) assigns jobs to work centers.

C) specifies the order in which jobs should be done at each center.

D) assigns workers to jobs.

E) assigns workers to machines.



Answer: C) specifies the order in which jobs should be done at each center.

Which of the following dispatching rules ordinarily gives the best results when the criterion is lowest time for completion of the full sequence of jobs?

Which of the following dispatching rules ordinarily gives the best results when the criterion is lowest time for completion of the full sequence of jobs?



A) shortest processing time (SPT)

B) critical ratio (CR)

C) first in, first out (FIFO)

D) first come, first served (FCFS)

E) longest processing time (LPT)



Answer: A) shortest processing time (SPT)

EDD stands for what?

EDD stands for what?



A) earliest due date

B) earliest design date

C) earliest detrimental date

D) earliest decision date

E) economic date determination



Answer: A) earliest due date

If an assignment problem consists of 5 workers and 4 projects:

If an assignment problem consists of 5 workers and 4 projects:



A) one worker will not get a project assignment.

B) one project will be assigned two workers.

C) the fifth worker will split time among the four projects.

D) one project will not get a worker assigned.

E) The problem cannot be solved by assignment method.



Answer: A) one worker will not get a project assignment.

If an assignment problem consists of 6 workers and 7 projects:

If an assignment problem consists of 6 workers and 7 projects:



A) one worker will not get a project assignment.

B) one worker will be assigned two projects.

C) each worker will contribute work toward the seventh project.

D) one project will not get a worker assigned.

E) The problem cannot be solved by assignment method.



Answer: D) one project will not get a worker assigned.