If an assignment problem consists of 5 workers and 4 projects:

If an assignment problem consists of 5 workers and 4 projects:



A) one worker will not get a project assignment.

B) one project will be assigned two workers.

C) the fifth worker will split time among the four projects.

D) one project will not get a worker assigned.

E) The problem cannot be solved by assignment method.



Answer: A) one worker will not get a project assignment.