Which of the following is an aid used to monitor jobs in progress?
A) a Gantt load chart
B) the assignment method
C) a Gantt schedule chart
D) Johnson's rule
E) a Gantt progress chart
Answer: C) a Gantt schedule chart
Management Chapter | Multiple Choice | Questions and Answers | Test Bank
A) a Gantt load chart
B) the assignment method
C) a Gantt schedule chart
D) Johnson's rule
E) a Gantt progress chart
Answer: C) a Gantt schedule chart