The WBS is a _______ of the work to be executed by the project team and defines the total scope of the project.

The WBS is a _______ of the work to be executed by the project team and defines the total scope of the project.



A. Vertical decomposition
B. Hierarchical decomposition
C. Horizontal decomposition
D. Critical decomposition


Answer: B