A. It may be scheduled or random
B. It may be conducted by external auditors
C. It may be conducted by internal auditors
D. It should be conducted by the project team itself
Quality Audit is a structured, independent process too.
A. Determine process compliance
B. Detect the problems caused by project team
C. Identify the root causes of problem
D. Determine the acceptability of the work product
A. Keeping errors out of the process
B. Keeping errors out of the hands of the customer
C. Keeping errors out of the targeted goal
D. Keeping errors out of the product
Which of the following is an example of the cost of quality?
A. Inspecting your product to be sure that it meets requirements.
B. Reviewing documents used to produce your product to be sure that they do not have defects.
C. Training your team on techniques that will help them avoid defects.
D. All of the answers
What is the benefit of continuous process improvement?
A. Remove activities that do not add value
B. Remove activities related to processes
C. Remove activities that the team hates to do
D. Enforce activities that the quality assurance department wants to do