Short-term schedules are prepared:

Short-term schedules are prepared:



A) directly from the aggregate plans.

B) directly from the capacity plans.

C) from inventory records for items that have been used up.

D) from master schedules, which are derived from aggregate plans.

E) from the purchasing plans.



Answer: D) from master schedules, which are derived from aggregate plans.