Which of the following best describes a gross material requirements plan?
A) a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started
B) an intermediate range plan for the scheduling of families of products
C) a chart illustrating whether capacity has been exceeded
D) a table that corrects scheduled quantities for inventory on hand
E) a schedule showing which products are to be manufactured and in what quantities
Answer: A