If the data source to refer is not available at estimation time, what should the Project Manager do?
A. The Project manager can base the estimation on industry standards or suggestions from an experienced person
B. Get approval from FSU Delivery Head before applying data that does not exist in PCB
C. Both A & B are correct
D. Both A & A are not correct
Answer: C