Lead time for cakes is 2 days with daily demand of 10 cakes and a safety stock of ½ a day. Each container (kanban) holds 1 cake. What is the correct number of kanbans?

Lead time for cakes is 2 days with daily demand of 10 cakes and a safety stock of ½ a day. Each container (kanban) holds 1 cake. What is the correct number of kanbans?



A) 4
B) 1
C) 5
D) 10
E) 25


Answer: E