Which of the following actions is consistent with the use of level scheduling?
A) use inventory to meet demand requirements
B) use overtime to meet higher-than-average demand requirements
C) vary production levels to meet demand requirements
D) vary work force to meet demand requirements
E) none of the above
Answer: A) use inventory to meet demand requirements