Which of the following actions is consistent with the use of level scheduling?

Which of the following actions is consistent with the use of level scheduling?


A) use inventory to meet demand requirements

B) use overtime to meet higher-than-average demand requirements

C) vary production levels to meet demand requirements

D) vary work force to meet demand requirements

E) none of the above



Answer: A) use inventory to meet demand requirements