A work center had planned outputs of 10, 15, 13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. What is the cumulative deviation in output?
A) 0
B) 1
C) -1
D) 58
E) Unable to determine with the given information
Answer: C) -1
Management Chapter | Multiple Choice | Questions and Answers | Test Bank
A) 0
B) 1
C) -1
D) 58
E) Unable to determine with the given information
Answer: C) -1