A work center had actual input of 280 hours and actual output of 270 hours. What is the change in backlog?

A work center had actual input of 280 hours and actual output of 270 hours. What is the change in backlog?



A) 10

B) -10

C) 0

D) 1.037

E) Unable to determine with the given information



Answer: A) 10