In using the systematic layout planning (SLP) technique, there is a need for nonproduction space that must be planned in addition to the production space required. SLP uses a specific graphic to record the desirability of these areas to be next to another area. This chart is called:

In using the systematic layout planning (SLP) technique, there is a need for nonproduction space that must be planned in addition to the production space required. SLP uses a specific graphic to record the desirability of these areas to be next to another area. This chart is called:


A. space relationship diagram

B. flow diagram

c. an activity relationship chart

d. from to chart



Answer: C