What is the value of Requirement Completeness for the following project?

What is the value of Requirement Completeness for the following project?



- Sprint 1: passed the accepted definition
- Sprint 2: passed the accepted definition
- Sprint 3: did not pass the accepted definition
- Sprint 4: passed the accepted definition
- Sprint 5: did not pass the accepted definition"


A. 40%
B. 60%
C. 80%
D. 100%"



Answer: B