A cost performance index (CPI) of 0.89 means:

A cost performance index (CPI) of 0.89 means:



A. At this time, we expect the total project to cost 89 percent more than planned.
B. When the project is completed, we will have spent 89 percent more than planned.
C. The project is progressing at 89 percent of the rate planned.
D. The project is getting 89 cents out of every dollar invested.




Answer: D