The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?

The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this? 



A. Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs





Answer: C