The project manager and project team are attempting to determine how much it will cost to complete all project activities. Which of the following tools and techniques would they not use in the process in which they are engaged?

The project manager and project team are attempting to determine how much it will cost to complete all project activities. Which of the following tools and techniques would they not use in the process in which they are engaged? 



A. Funding limit reconciliation
B. Vendor bid analysis
C. Cost of quality
D. Project management software



Answer: A