How is a Post-Mortem meeting considered on- time?
A. If it's conducted before or equal to project actual end date
B. If it's conducted before or equal to project planned end date
C. If it's conducted within 15 working days from project planned end date
D. If it's conducted within 10 working days from project planned end date"
Answer: B