Demand for dishwasher water pumps is 8 per day. The standard deviation of demand is 3 per day, and the order lead time is four days. The service level is 95%. What should the reorder point be?
A) about 18
B) about 24
C) about 32
D) about 38
E) more than 40
Answer: E