"Effort to control schedule when the project is using a change-driven approach such as Agile includes ____________________ ."

"Effort to control schedule when the project is using a change-driven approach such as Agile includes ____________________ ."



A. Quality Up activities
B. Critical Chain
C. Create WBS
D. Identifying & managing changes as they arise


Answer: D