"If the team is decomposing work packages into the activities required to produce them, they are in ____________________ ."

"If the team is decomposing work packages into the activities required to produce them, they are in ____________________ ."



A. Create WBS process
B. Define Activities process
C. Develop Schedule process
D. Control Schedule process


Answer: B