Which is additional activity involved in controlling the schedule? Project Software Estimation Scope Management Time Which is additional activity involved in controlling the schedule? A. Inspect deliverables B. Review project Chapter C. Follow the change control process D. Q-up Answer: C Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+