If resources are assigned to the tasks, what may the Project Manager cause when shortening the duration of tasks on the critical path?

If resources are assigned to the tasks, what may the Project Manager cause when shortening the duration of tasks on the critical path?



A. Resource over allocated on fixed-work tasks
B. Nothing happens
C. The finish date of the schedule occurs sooner
D. None of the answer


Answer: A