If resources are assigned to the tasks, what may the Project Manager cause when shortening the duration of tasks on the critical path?
A. Resource over allocated on fixed-work tasks
B. Nothing happens
C. The finish date of the schedule occurs sooner
D. None of the answer
Answer: A