Project A has scope: DDD, Coding, Unit test. The Project Manager did the estimation version 1.0 in the Planning phase. When should the Project Manager re-estimate?
A. Once design is completed
B. Once code is completed
C. Once change requests are received
D. All of the answers
Answer: D