The Create WBS process identifies the deliverables at the____________________ level in the Work Breakdown Structure (WBS). Project Software Estimation Scope Management Time The Create WBS process identifies the deliverables at the____________________ level in the Work Breakdown Structure (WBS). A. Medium B. Average C. Lowest D. Highest Answer: C Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+