In Fsoft projects, the exposure/ priority of risk could be based on __________________.

In Fsoft projects, the exposure/ priority of risk could be based on __________________.



A. Impact & Severity
B. Serious & Urgent
C. Impact & Probability
D. Fatal & Important


Answer: C