The correct sequence from longest to smallest duration scheduling is:

The correct sequence from longest to smallest duration scheduling is:



A) capacity planning, aggregate planning, master schedule, short-term scheduling.

B) aggregate planning, capacity planning, master schedule, short-term scheduling.

C) master schedule, capacity planning, aggregate planning, short-term scheduling.

D) master schedule, aggregate planning, capacity planning, short-term scheduling.

E) capacity planning, master schedule, aggregate planning, short-term scheduling.



Answer: A) capacity planning, aggregate planning, master schedule, short-term scheduling.