Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. What is the crossover point between process A and process B?

Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. What is the crossover point between process A and process B?




A) 50 units
B) 200 units
C) $2,500
D) $5,000
E) $9,500


Answer: A