The project sponsor asks the project manager to determine the cost performance needed with the remaining project resources in order to meet the project goal. The project is scheduled to take two years to complete and cost $1 million. Eight months into the project, $300,000 has been spent and 35 percent of the work has been completed. The project manager believes that the $1 million figure will remain viable for the remainder of the project. Which of the following answers would best help the project manager answer the sponsor's question?

The project sponsor asks the project manager to determine the cost performance needed with the remaining project resources in order to meet the project goal. The project is scheduled to take two years to complete and cost $1 million. Eight months into the project, $300,000 has been spent and 35 percent of the work has been completed. The project manager believes that the $1 million figure will remain viable for the remainder of the project. Which of the following answers would best help the project manager answer the sponsor's question?




A. TCPI=0.93
B. CPI=1.17
C. TCPI= 1.08
D. CPI=0.86



Answer: A


Learn More :