Cost Management Chapter 7
You are building a house. You need to estimate the costs for the foundation. You have the following data: 30 cubic yards (CY) of soil to be removed; 2,600 pounds of steel rebar to be installed; and 20 CY of concrete to be placed. Soil removal costs $100/CY; steel rebar cost $1.50/pound installed, and concrete costs $400/CY placed. Which of the following is the best estimate of the cost of building the foundation for the house?
You are building a house. You need to estimate the costs for the foundation. You have the following data: 30 cubic yards (CY) of soil to be removed; 2,600 pounds of steel rebar to be installed; and 20 CY of concrete to be placed. Soil removal costs $100/CY; steel rebar cost $1.50/pound installed, and concrete costs $400/CY placed. Which of the following is the best estimate of the cost of building the foundation for the house?
You are building a house. You need to estimate the costs for the foundation. You have the following data: 30 cubic yards (CY) of soil to be removed; 2,600 pounds of steel rebar to be installed; and 20 CY of concrete to be placed. Soil removal costs $100/CY; steel rebar cost $1.50/pound installed, and concrete costs $400/CY placed. Which of the following is the best estimate of the cost of building the foundation for the house?
A. $8,800
B. $14,900
C. $9,600
D. $12,400
Answer: B
Learn More :