The project manager is creating the cost management plan for the project. Which of the following tools and techniques would she not use to create the plan?

The project manager is creating the cost management plan for the project. Which of the following tools and techniques would she not use to create the plan? 



A. Bottom-up estimating
B. Expert judgment
C. Meetings
D. Analytical techniques




Answer: A


Learn More :