The project manager and project team are beginning to estimate the costs of the project. Which of the following documents should they consult to learn about funding constraints?

The project manager and project team are beginning to estimate the costs of the project. Which of the following documents should they consult to learn about funding constraints?




A. Scope statement
B. WBS
C. Cost baseline
D. Life cycle cost




Answer: A


Learn More :