The project manager leading a factory renovation project internal to the organization has been asked to take life-cycle costs into account when making decisions that will affect the project. Which of the following statements should give the project manager the most cause for concern?

The project manager leading a factory renovation project internal to the organization has been asked to take life-cycle costs into account when making decisions that will affect the project. Which of the following statements should give the project manager the most cause for concern? 




A. The project team has consumed most of the project budget performing the work of the project.
B. The project team has made keeping short-term project costs low its highest priority.
C. The cost of operating and maintaining the factory exceeds the budget for the project.
D. The project team will be disbanded before maintenance on the factory will be required.



Answer: B