You are a foundation contractor. Over many projects of a certain size, you have developed a cost factor a $400 per linear foot of foundation. Which estimating technique are you using?
You are a foundation contractor. Over many projects of a certain size, you have developed a cost factor a $400 per linear foot of foundation. Which estimating technique are you using?
You are a foundation contractor. Over many projects of a certain size, you have developed a cost factor a $400 per linear foot of foundation. Which estimating technique are you using?
A. Detailed
B. Bottom-up
C. Parametric
D. Sum of the squares
Answer: C