The cost contingency reserve should be:

The cost contingency reserve should be: 



A. Hidden to prevent management from disallowing the reserve.
B. Added to each activity to provide the customer with a shorter critical path.
C. Maintained by management to cover cost overruns.
D. Added to the costs of the project to account for risks.




Answer: D