The cost contingency reserve should be:
A. Hidden to prevent management from disallowing the reserve.
B. Added to each activity to provide the customer with a shorter critical path.
C. Maintained by management to cover cost overruns.
D. Added to the costs of the project to account for risks.
Answer: D