Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:

Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:




A. Agree to analogous estimating, as it is a form of expert judgment.
B. Suggest life cycle costing as a compromise.
C. Determine why the sponsor wants such an accurate estimate.
D. Try to convince the sponsor to allow expert judgment because it is typically more accurate.




Answer: A